The Miller Act is the federal law that requires prime contractors on federal construction projects to post two bonds: a performance bond that protects the government if the work isn't finished, and a payment bond that protects the subcontractors, laborers, and suppliers who furnish labor and materials for the job. First passed in 1935 and now codified at 40 U.S.C. chapter 31, subchapter III (the FAR calls it the "Bonds statute"), it applies to federal construction contracts exceeding $150,000 under FAR 28.102-1.
For subcontractors and suppliers, the payment bond matters for a simple reason. If the prime contractor doesn't pay, the payment bond, backed by a surety company, gives them a claim they can enforce in federal court. Here is how it works, what the deadlines are, and what both primes and trade partners should know.
What the Miller Act requires
Two bonds on contracts over $150,000
Under FAR 28.102-1, performance and payment bonds are required for any construction contract exceeding $150,000. The requirement can be waived only in narrow cases, such as work performed in a foreign country where the contracting officer finds bonding impracticable. The bonds, including any reinsurance agreements, must be furnished before the contractor receives a notice to proceed or is allowed to start work.
The statute describes the two bonds this way in 40 U.S.C. 3131:
- Performance bond: protects the government. If the prime contractor fails to perform, the surety is on the hook.
- Payment bond: protects "all persons supplying labor and material in carrying out the work provided for in the contract."
The statute also requires every performance bond to cover federal taxes withheld from the wages the contractor pays on the job.
How big the bonds are
FAR 28.102-2 sets the amounts. Unless the contracting officer decides a lower amount is adequate, the performance bond equals 100 percent of the original contract price. The payment bond also equals 100 percent of the original contract price unless the contracting officer makes a written determination, supported by specific findings, that this is impractical. Either way, the payment bond can't be less than the performance bond. If the contract price increases, the government can require additional bond protection equal to 100 percent of the increase.
The FAR clause that puts this into a contract is 52.228-15, Performance and Payment Bonds - Construction. It uses Standard Form 25 for the performance bond and Standard Form 25A for the payment bond.
Smaller contracts: alternative payment protections
For construction contracts greater than $35,000 but not greater than $150,000, FAR 28.102-1 still protects the people doing the work. The contracting officer selects two or more payment protections, and the contractor furnishes one of them. The options are:
- A payment bond
- An irrevocable letter of credit
- A tripartite escrow agreement among the prime, a federally insured bank, and the suppliers of labor and material
- Certificates of deposit deposited with the contracting officer
- Certain other deposits of security listed in FAR 28.204
These contracts use the clause at FAR 52.228-13, Alternative Payment Protections.
Who can be a surety
The surety stands behind the bond, so the government is selective. Under FAR 28.202, corporate sureties on bonds for work in the United States must appear on the Treasury Department's list of approved sureties, Circular 570. The Treasury publishes and updates that list online.
How the payment bond protects subcontractors and suppliers
Who can make a claim
Under 40 U.S.C. 3133, the payment bond protects two groups:
- First-tier claimants: anyone with a direct contract with the prime contractor, such as a subcontractor or a supplier selling straight to the prime.
- Second-tier claimants: anyone with a direct contract with a subcontractor but no contract with the prime. These claimants have an extra step, described below.
The 90-day and one-year deadlines
The deadlines are short and strict, so it pays to know them before you start work.
- When you can sue: a claimant who hasn't been paid in full within 90 days after the day it performed the last of its labor or supplied the last of its material may bring a civil action on the payment bond.
- Notice for second-tier claimants: a claimant without a contract with the prime must give the prime contractor written notice within 90 days of its last labor or material. The notice must state the amount claimed with substantial accuracy and name the party the work or material was for. It must be delivered by a method that provides written, third-party verification of delivery, or in a way a U.S. marshal could serve a summons.
- Where and when to file: the lawsuit is brought in the name of the United States for the use of the claimant, in the U.S. district court for the district where the contract was performed, regardless of the amount. It must be filed no later than one year after the last labor was performed or material was supplied.
The government itself isn't liable for the costs of these lawsuits. The claim runs against the bond and the surety.
Your rights can't be signed away in advance
A waiver of the right to sue on a Miller Act payment bond is void unless it is in writing, signed by the person giving up the right, and executed after that person has already furnished labor or material on the contract. A clause in a subcontract signed before any work starts can't take this protection away.
Getting a copy of the bond
You don't have to guess who the surety is. Under FAR 28.106-6, a subcontractor or supplier, or a prospective one, can ask the contracting officer for the name and address of the surety, the penal amount of the payment bond, and a copy of the bond. The contracting officer may charge reasonable copying fees. Under 40 U.S.C. 3133, an unpaid claimant who submits an affidavit can also get a certified copy of the bond and the contract.
This article is general information, not legal advice. If you are facing a payment dispute, talk to a construction attorney early, because the deadlines don't wait.
What this means for small contractors
For a prime contractor, bonding capacity is part of being ready to bid on federal construction. A surety evaluates a contractor before issuing bonds, and the SBA's Surety Bond Guarantee program helps small businesses that might not meet other sureties' criteria. According to the SBA, it guarantees bid, performance, payment, and ancillary bonds on federal contracts of up to $14 million, and it charges a guarantee fee of 0.6 percent of the contract price on performance and payment bonds, with no fee for bid bond guarantees.
For trade partners, the Miller Act is one of the reasons federal work can be a solid market. But the best protection is still a prime that pays on time and communicates clearly. We believe integrity and honest communication are the foundation of a good project, and paying the people who do the work is part of serving them well.
Join TTH's vendor list
TTH is a federal general contractor headquartered in the Dallas-Fort Worth area, supporting federal projects nationwide under primary NAICS code 236220. If you are a specialty trade subcontractor, such as concrete, site work, electrical, plumbing, HVAC, painting, or finishing, or you supply materials and equipment for federal construction, join our vendor and subcontractor list on the Partner With Us page. We'll reach out when an opportunity matches your trade and service area.
Frequently asked questions
What is the Miller Act?
The Miller Act is a 1935 federal law, now codified at 40 U.S.C. 3131-3134, that requires prime contractors on federal construction contracts to furnish a performance bond protecting the government and a payment bond protecting people who supply labor and materials for the work.
What is the Miller Act bond threshold?
Under FAR 28.102-1, performance and payment bonds are required for federal construction contracts exceeding $150,000. For construction contracts over $35,000 but not over $150,000, the contracting officer must select two or more alternative payment protections, such as a payment bond or an irrevocable letter of credit, and the contractor furnishes one of them.
How much is a Miller Act payment bond?
Under FAR 28.102-2, the payment bond normally equals 100 percent of the original contract price, plus 100 percent of any increase, unless the contracting officer makes a written determination that this amount is impractical. The payment bond can never be less than the performance bond.
How long does a subcontractor have to file a Miller Act claim?
Under 40 U.S.C. 3133, a claimant who has not been paid in full within 90 days after its last labor or material may sue on the payment bond, and the lawsuit must be filed no later than one year after that last day of work or delivery. It is filed in federal district court in the name of the United States for the use of the claimant.
Can a second-tier subcontractor make a Miller Act claim?
Yes. A person with a direct contract with a subcontractor, but no contract with the prime contractor, can sue on the payment bond if it gives the prime contractor written notice within 90 days of its last labor or material. The notice must state the amount claimed with substantial accuracy and name the party it worked for or supplied.
How do I find the surety on a federal construction project?
Ask the contracting officer. Under FAR 28.106-6, a subcontractor or supplier, or a prospective one, can request the name and address of the surety, the penal amount of the payment bond, and a copy of the bond. The contracting officer may charge reasonable copying fees.
Sources
- Acquisition.gov: FAR 28.102-1, Performance and payment bonds for construction contracts (General)
- Acquisition.gov: FAR 28.102-2, Amount required
- Acquisition.gov: FAR 28.102-3, Contract clauses
- Acquisition.gov: FAR 28.106-6, Furnishing information
- Acquisition.gov: FAR 28.202, Acceptability of corporate sureties
- Acquisition.gov: FAR 52.228-15, Performance and Payment Bonds - Construction
- Cornell LII: 40 U.S.C. 3131, Bonds of contractors of public buildings or works
- Cornell LII: 40 U.S.C. 3133, Rights of persons furnishing labor or material
- U.S. Treasury: Circular 570, approved sureties on federal bonds
- SBA: Surety Bond Guarantee program