Cash flow is one of the first things any contractor thinks about before taking on a federal construction job. Materials, labor, and equipment have to be paid for long before a building is finished, so knowing how and when the government pays is part of good project management. On most fixed-price federal construction contracts, the answer is progress payments: monthly payments, based on approved estimates of the work done so far, governed by two clauses in the Federal Acquisition Regulation (FAR).
This post walks through how those payments work, what retainage means, how fast the government has to pay, and what the rules mean for subcontractors and suppliers further down the chain.
The two clauses that control payment
Two FAR clauses do most of the work:
- FAR 52.232-5, Payments under Fixed-Price Construction Contracts, explains how progress payments are requested, certified, retained, and finalized.
- FAR 52.232-27, Prompt Payment for Construction Contracts, sets due dates, interest penalties, and the rules primes must pass down to their subcontractors.
Read together, they describe a payment cycle that moves from the government to the prime, and from the prime to every tier of subcontractor and supplier.
How progress payments are requested
Under FAR 52.232-5, the government makes progress payments monthly as the work proceeds, or more often if the contracting officer decides. Payments are based on estimates of work accomplished that meets the quality standards in the contract, as approved by the contracting officer.
Each request has to be backed up. The clause requires:
- An itemization of the amounts requested, tied to the elements of work in the contract.
- The amount included for work performed by each subcontractor.
- The total amount of each subcontract.
- The amounts previously paid to each subcontractor.
- Any additional supporting data the contracting officer requires.
The contracting officer may also allow material delivered to the site and preparatory work to count toward the estimate. Material stored somewhere else can count only if the contract specifically authorizes it and the contractor shows it holds title to the material and will use it on the contract.
The payment certification
Every request must include a signed certification, or payment will not be made. The contractor certifies, to the best of its knowledge and belief, that the amounts requested are only for performance under the contract, that all payments due to subcontractors and suppliers from previous payments have been made, and that timely payments will be made from the new payment. It also certifies that the request does not include amounts the prime intends to withhold from a subcontractor under the subcontract.
That certification matters. If a contractor later finds it was paid for work that did not conform to the contract, it must notify the contracting officer and owes the government interest on the unearned amount until the problem is fixed or a later request is reduced.
Retainage: what it is and when it applies
Retainage is money held back from a progress payment. On federal construction, it is not automatic. FAR 52.232-5 says that if satisfactory progress was made during the period, the contracting officer shall authorize payment in full. Only when satisfactory progress has not been made may the contracting officer retain up to 10 percent of the payment until progress improves.
FAR 32.103 adds guidance for contracting officers: retainage should not be used as a substitute for good contract management, funds should not be withheld without cause, and decisions are made case by case. When work is substantially complete, the contracting officer keeps only what is adequate to protect the government and releases the rest. Retained amounts must be paid promptly once all contract requirements are complete.
Two other details are worth knowing. Upon request, the government reimburses premiums paid for performance and payment bonds once the contractor shows the surety was paid in full, and retainage does not apply to that portion. And when a separately priced building or division of work is completed and accepted, it is paid without a percentage retained.
How fast the government has to pay
FAR 52.232-27 sets the clock. For a progress payment, the due date is 14 days after the designated billing office receives a proper payment request. Retained amounts are due as stated in the contract or, if the contract is silent, 30 days after the contracting officer approves their release. Final payment is due on the later of 30 days after a proper invoice is received or 30 days after the government accepts the work.
A proper invoice has to include specific items, such as the contract number, a description of the work, the substantiation and certification required by FAR 52.232-5, and correct electronic funds transfer information. If an invoice is not proper, the billing office must return it within 7 days with the reasons.
If the government pays late and the conditions in the clause are met, the payment office pays an interest penalty automatically, without the contractor having to ask. Interest is not owed when the delay comes from a disagreement over the amount, quality, or contract compliance, or on amounts properly retained under the contract.
What the rules mean for subcontractors and suppliers
The part of FAR 52.232-27 that matters most to trade partners is paragraph (c). The prime must include in every subcontract, including material supply agreements:
- A payment clause requiring the prime to pay the subcontractor for satisfactory performance no later than 7 days after receiving payment from the government.
- An interest penalty clause for late payments, computed at the rate set by the Secretary of the Treasury.
- A flowdown clause requiring each subcontractor to include the same terms in its own subcontracts, all the way down the chain.
Subcontracts may still allow retainage and withholding if the parties agree to it. But to withhold for a performance problem without owing interest, the prime must send the subcontractor a written notice, with a copy to the contracting officer, stating the amount, the specific causes, and the remedial actions needed to get paid. After the deficiency is corrected, the prime generally must pay within 7 days or owe interest.
If a subcontractor or supplier is not paid, FAR 32.112-1 lets it bring that to the contracting officer. The contracting officer may check whether the prime complied with the Prompt Payment Act and whether its payment certification was accurate, encourage payment, or, where the payment clauses allow, reduce or suspend progress payments to the prime.
Practical tips for trade partners
- Read your subcontract's payment terms, retainage, and withholding language before you sign.
- Submit clean, timely pay applications that match the schedule of values, so the prime can include your work in its monthly request.
- Keep daily records and photos that support the percentage of work you bill.
- Track when the prime is paid and when your 7-day window starts and ends.
- Make sure your remittance and banking information is current so payment is never held up by paperwork.
At TTH, we believe paying partners on time is a matter of integrity and clear communication, not just a contract clause. Treating the people who build alongside us fairly is part of serving well.
Join TTH's vendor list
TTH is a federal general contractor headquartered in the Dallas-Fort Worth area, supporting federal projects nationwide under primary NAICS code 236220. If you are a specialty trade subcontractor or supplier who keeps clean records and wants to grow in federal construction, join our vendor and subcontractor list on the Partner With Us page. We'll reach out when an opportunity fits your trade and service area.
Frequently asked questions
How often are progress payments made on federal construction contracts?
Under FAR 52.232-5, Payments under Fixed-Price Construction Contracts, the government makes progress payments monthly as the work proceeds, or at more frequent intervals if the contracting officer decides. Payments are based on estimates of work accomplished that meets the contract's quality standards, as approved by the contracting officer.
How much retainage can the government hold on a federal construction contract?
If satisfactory progress has not been made, the contracting officer may retain a maximum of 10 percent of a progress payment until satisfactory progress is achieved. When progress is satisfactory, FAR 52.232-5 says the payment is authorized in full, and FAR 32.103 says retainage should not substitute for good contract management.
How fast does the government have to pay a federal construction progress payment?
FAR 52.232-27, Prompt Payment for Construction Contracts, sets the due date for a progress payment at 14 days after the designated billing office receives a proper payment request. If payment is late and the conditions in the clause are met, the government pays an interest penalty automatically, without the contractor having to ask.
How quickly must a prime contractor pay subcontractors on a federal construction job?
FAR 52.232-27 requires the prime to include a clause in each subcontract obligating it to pay the subcontractor for satisfactory performance no later than 7 days after receiving payment from the government. Late payments carry an interest penalty at the rate set by the Treasury, and the same clauses must flow down to lower-tier subcontractors and suppliers.
Can a prime contractor withhold payment from a subcontractor on a federal project?
Yes, if the subcontract allows it, but FAR 52.232-27 requires a written notice to the subcontractor, with a copy to the contracting officer, stating the amount withheld, the specific causes, and the remedial actions needed to get paid. Once the deficiency is corrected, the prime generally must pay within 7 days or owe interest.
What can a subcontractor do if a federal prime contractor does not pay?
Under FAR 32.112-1, a subcontractor or supplier can tell the contracting officer it has not been paid. The contracting officer may check whether the prime complied with the Prompt Payment Act and whether its payment certification was accurate, and may encourage payment or, if the payment clauses allow, reduce or suspend progress payments to the prime.
Sources
- Acquisition.gov: FAR 52.232-5, Payments under Fixed-Price Construction Contracts
- Acquisition.gov: FAR 52.232-27, Prompt Payment for Construction Contracts
- Acquisition.gov: FAR 32.103, Progress payments under construction contracts
- Acquisition.gov: FAR 32.112-1, Subcontractor assertions of nonpayment